Civil construction for the Al-Rifai and Al-Waha 11/33 kV substations for Sadeer General Investments, covering site preparation, control and guard buildings, transformer yards and cable trenches, together with water, drainage, lighting and associated services.
01
Site preparation, surveying, compaction and soil treatment based on testing.
02
Construction of control/equipment and guard buildings and perimeter fencing.
03
Transformer yards, cable trenches and associated items, and the fire wall.
04
Water-tank bases and structures, collection tanks, and water and drainage services.
05
External lighting and the electrical, water and sanitary installations covered by the contract.